Peninsula Clarion
Kenai Airport Explores Electric Cargo Service amid FAA Delays
November 20, 2026
  • Share
  • Battery-powered cargo planes could be a new arrival at Kenai Municipal Airport, where officials are considering an aircraft charging station while working to preserve space for future terminal expansion.

    Airport Manager Rick Johnson told the Kenai Airport Commission on Nov. 12, that representatives from BETA Technologies recently visited the airfield to discuss installing charging equipment for a potential electric cargo operation connecting Kenai with two other airports.

    The Vermont-based manufacturer hopes to partner with a cargo operator to fly the route using its ALIA CX300, an electric aircraft that takes off and lands on conventional runways.

    Johnson said the company would cover the installation costs if the project moves forward, with a possible timeline of about one year.

    According to Johnson, the most convenient site for accessing three-phase electrical power is south of the terminal. However, installing a charging station there could interfere with future expansion. Airport officials have identified other potential locations but are leaving further evaluation to BETA before deciding how to proceed.

    “We’re not going to allow it to impact current operations,” Johnson said.

    The proposal is part of a push to expand electric aviation on shorter regional routes, particularly in places like Alaska, where many communities rely on air travel to transport people and supplies.

    BETA’s CX300 is designed to transport passengers or cargo over routes of approximately 215 nautical miles under its stated operating assumptions. The company has conducted flight demonstrations across the United States, although the aircraft has not yet received full Federal Aviation Administration (FAA) certification for routine commercial service.

    The concept has already attracted interest in Alaska. In September 2025, cargo carrier Ryan Air ordered electric aircraft from BETA and expressed interest in building charging infrastructure, an early indication of how the technology could eventually serve rural communities across the state.

    Landing system awaits inspection

    While the airport considers bringing a new type of aircraft to the Kenai Peninsula, work continues on restoring equipment used by conventional flights.

    Kenai’s main runway reopened Oct. 2 after undergoing reconstruction that began in May, during which the aircraft used Taxiway Alpha as a temporary runway. However, the airport’s instrument landing system, which provides pilots with guidance when approaching a runway in poor visibility, has not yet returned to service.

    Johnson said two lights damaged during construction have since been replaced, and until those repairs were completed, the FAA could not schedule the required flight inspection. The inspection aircraft had already left Alaska, and officials are now working with the agency to arrange its return.

    “They needed the full services to perform a flight check to get the ILS up and running,” Johnson said.

    Airport officials hope the inspection can take place before the end of November, but Johnson cautioned that the timing depends on the FAA’s availability.

    In the meantime, pilots can continue using satellite-based navigation procedures. The ILS outage does not mean the airport is closed, although it leaves one of its established instrument approaches unavailable until the federal inspection is completed.

    One commissioner suggested formally designating Taxiway Alpha as a backup runway in case the main runway becomes unusable. The additional work could cost about $10,000, but no action was taken on the proposal.

    Improvements and digital tower

    On another front, Johnson said the first phase of the airport master plan has been completed, with staff preparing the final paperwork needed to close out its grant. The next phase will establish project schedules, funding requirements and cost estimates for planned improvements.

    Proposed work includes rebuilding Taxiway Alpha and other taxiways, while city officials plan to meet with the FAA to discuss which projects could receive funding over the next three years.

    The airport is proceeding with Alternative 4 of its master plan, which was selected by city officials and commissioners, although additional FAA comments are still pending.

    Construction of a new perimeter fence is scheduled to begin in April 2027 and wrap up by September, as staff are reviewing an updated stormwater pollution prevention plan before submitting it to the state.

    In a separate update, commissioners discussed the airport’s remote air traffic control tower system, which uses cameras and electronic displays to help controllers monitor aircraft movements.The FAA announced Nov. 6 that digital tower systems at Kenai and Bartow Executive Airport in Florida had entered operational service. Johnson, however, described Kenai’s installation during Thursday’s meeting as still undergoing testing and awaiting additional fiber-optic connections.

    He said discussions were being arranged to determine how to proceed.

    Beyond those aviation projects, commissioners unanimously recommended that the Kenai City Council adopt the city’s updated 2026 Land Management Plan, covering 376 city-owned parcels, including property associated with the airport and submerged tidelands.

    A significant portion of those holdings are maintained for the benefit of the airport, meaning proceeds from their lease or sale can support airport operations and improvements.

    Planning Director Kevin Buettner said the city began updating the inventory in June to account for property sales, new acquisitions and corrections to borough parcel records.

    The revised plan replaces the previous system of describing properties as retained or available for disposal with more specific recommendations identifying possible public use, leasing, sale or partial development.

    For example, some airport-related parcels may be available for lease but cannot be sold under the conditions attached to their federal release. Others are unavailable because they are already leased or designated for a particular public purpose.

    Buettner emphasized that the changes do not alter existing zoning classifications or automatically authorize development. Instead, the document is intended to help residents and potential developers understand which properties could be available and what restrictions apply.

    The updated inventory includes 44 maps. Once the plan is adopted, staff intend to publish the document online and eventually provide an interactive version allowing users to select individual parcels and review their information. The city hopes to finish that digital resource by the end of the fiscal year in June 2027.

    During the discussion, commissioners asked about approximately five acres near the Civil Air Patrol facility that had previously been considered for a possible change in ownership or boundaries.

    According to Buettner, the federal government reserved rights to the property when the airport was transferred to the city in 1963, and any effort to change that arrangement could involve a lengthy federal process. The city has temporarily set the proposal aside while considering other options.

    In other business, the commission unanimously recommended renewing the American Red Cross’s special use permit for approximately 475 square feet on the second floor of the Alaska Regional Fire Training Center. Under the renewal, the organization would continue paying $1 per month in rent, along with $211.44 per month for utilities. The Red Cross uses the facility to support its services on the Kenai Peninsula.

    With the commission’s decisions made, airport staff will continue working with the FAA on the landing system and capital projects while waiting for BETA Technologies to return with possible charging station locations.

    The Airport Commission’s next regular meeting is scheduled for Dec. 10.